Information is Courtesy of ARCO Design/Build, a major sponsor of the 2023 SIOR Southeastern Regional Conference.
Current Construction Material Lead Times as of August 2023:
SITE UTILITIES – CONCRETE PIPE & STRUCTURES | NORMALIZED |
SITE UTILITIES – CMP STORM PIPE | NORMALIZED |
SITE UTILITIES – DIP FIRE LINE | 12-14 WEEKS |
SITE UTILITIES – PVC FIRE LINE | 8-10 WEEKS |
STRUCTURAL STEEL | 12-14 WEEKS |
JOIST / DECK | 12-16 WEEKS |
ROOFING MATERIALS | 3-4 WEEKS |
OVERHEAD DOORS | 4-6 WEEKS |
MECHANICAL DOCK LEVELERS | 25-30 WEEKS |
DOCK SEALS | 8-10 WEEKS |
ESFR SPRINKLER PIPE | 2-4 WEEKS |
ELECTRIC FIRE PUMP | 6-10 WEEKS |
DIESEL FIRE PUMP | 22-24 WEEKS |
FIRE WATER STORAGE TANK | 12-14 WEEKS |
PLUMBING PVC – 6″ OR LESS | NORMALIZED |
HVAC – EXHAUST FANS | 16-18 WEEKS |
HVAC – CAMBRIDGE UNITS | 10-12 WEEKS |
HVAC – ROOF TOP AC UNITS | 22-24 WEEKS |
HVAC – LIEBERT UNITS (COMPUTER ROOM) | 52-60 WEEKS |
ELECTRICAL – SWITCHBOARDS | 52-60 WEEKS |
ELECTRICAL – PANELS (400AMPS OR LESS) | 8 WEEKS |
ELECTRICAL – PANELS (600 AMPS OR MORE) | 20-24 WEEKS |
ELECTRICAL – HI-BAY LIGHTS | 2-4 WEEKS |
ELECTRICAL – GENERATORS | 52-60 WEEKS |