Information is Courtesy of ARCO Design/Build, a major sponsor of the 2023 SIOR Southeastern Regional Conference.
Current Construction Material Lead Times as of August 2023:
| SITE UTILITIES – CONCRETE PIPE & STRUCTURES | NORMALIZED |
| SITE UTILITIES – CMP STORM PIPE | NORMALIZED |
| SITE UTILITIES – DIP FIRE LINE | 12-14 WEEKS |
| SITE UTILITIES – PVC FIRE LINE | 8-10 WEEKS |
| STRUCTURAL STEEL | 12-14 WEEKS |
| JOIST / DECK | 12-16 WEEKS |
| ROOFING MATERIALS | 3-4 WEEKS |
| OVERHEAD DOORS | 4-6 WEEKS |
| MECHANICAL DOCK LEVELERS | 25-30 WEEKS |
| DOCK SEALS | 8-10 WEEKS |
| ESFR SPRINKLER PIPE | 2-4 WEEKS |
| ELECTRIC FIRE PUMP | 6-10 WEEKS |
| DIESEL FIRE PUMP | 22-24 WEEKS |
| FIRE WATER STORAGE TANK | 12-14 WEEKS |
| PLUMBING PVC – 6″ OR LESS | NORMALIZED |
| HVAC – EXHAUST FANS | 16-18 WEEKS |
| HVAC – CAMBRIDGE UNITS | 10-12 WEEKS |
| HVAC – ROOF TOP AC UNITS | 22-24 WEEKS |
| HVAC – LIEBERT UNITS (COMPUTER ROOM) | 52-60 WEEKS |
| ELECTRICAL – SWITCHBOARDS | 52-60 WEEKS |
| ELECTRICAL – PANELS (400AMPS OR LESS) | 8 WEEKS |
| ELECTRICAL – PANELS (600 AMPS OR MORE) | 20-24 WEEKS |
| ELECTRICAL – HI-BAY LIGHTS | 2-4 WEEKS |
| ELECTRICAL – GENERATORS | 52-60 WEEKS |