Material Lead Times (August 2023)

A blue and white logo with the words material lead times


Information is Courtesy of ARCO Design/Build, a major sponsor of the 2023 SIOR Southeastern Regional Conference.

Current Construction Material Lead Times as of August 2023:

SITE UTILITIES – CONCRETE PIPE & STRUCTURES NORMALIZED
SITE UTILITIES – CMP STORM PIPE NORMALIZED
SITE UTILITIES – DIP FIRE LINE 12-14 WEEKS
SITE UTILITIES – PVC FIRE LINE 8-10 WEEKS
STRUCTURAL STEEL 12-14 WEEKS
JOIST / DECK 12-16 WEEKS
ROOFING MATERIALS 3-4 WEEKS
OVERHEAD DOORS 4-6 WEEKS
MECHANICAL DOCK LEVELERS 25-30 WEEKS
DOCK SEALS 8-10 WEEKS
ESFR SPRINKLER PIPE 2-4 WEEKS
ELECTRIC FIRE PUMP 6-10 WEEKS
DIESEL FIRE PUMP 22-24 WEEKS
FIRE WATER STORAGE TANK 12-14 WEEKS
PLUMBING PVC – 6″ OR LESS NORMALIZED
HVAC – EXHAUST FANS 16-18 WEEKS
HVAC – CAMBRIDGE UNITS 10-12 WEEKS
HVAC – ROOF TOP AC UNITS 22-24 WEEKS
HVAC – LIEBERT UNITS (COMPUTER ROOM) 52-60 WEEKS
ELECTRICAL – SWITCHBOARDS 52-60 WEEKS
ELECTRICAL – PANELS (400AMPS OR LESS) 8 WEEKS
ELECTRICAL – PANELS (600 AMPS OR MORE) 20-24 WEEKS
ELECTRICAL – HI-BAY LIGHTS 2-4 WEEKS
ELECTRICAL – GENERATORS 52-60 WEEKS

 